October 22, 2026
In the spring of 2012, the City of Spring Hill made a deal with Outdoor Encounter and its partners. If they raised $30,000 by July 1, the city would add up to $20,000 to build a short paved link between the Peter Jenkins Walking Trail in Wyngate Estates and the sidewalk at Allendale Elementary. The Williamson Herald reported that with less than two weeks left, about $25,000 had come in. Donors included the Spring Hill Rotary, the Allendale PTO, the Wyngate Estates HOA, corporate sponsors, and Peter Jenkins himself.
The project was small: about 700 feet of pavement and a 25-foot prefabricated bridge over a drainage swale. The paper reported that roughly half of Allendale's students lived in Wyngate and the neighborhoods next to it. Organizers wanted the link open by the first day of school.
Fourteen years later, the next piece of that same greenway is a federally funded connector under one mile long. In July 2026 it received its notice to proceed with design. The gap between those two timelines explains why Spring Hill's greenway map moves the way it does. Neighborhood links and road projects get built. The federal grant projects move through a fixed series of TDOT approvals, and both of the city's federal projects still have to buy right-of-way before construction can start.
In 2007, the Spring Hill Board of Mayor and Aldermen passed Resolution 07-04. It recognized Peter Jenkins as a long-time resident and nationally known bestselling author who moved to Spring Hill in 1982. His publisher, Macmillan, notes that A Walk Across America, his 1979 account of his first cross-country trip, spent three months on The New York Times bestseller list.
A walking trail named for a man known for walking a continent is now a project where each half-mile of design needs a sign-off from Nashville.
The city's 2023 request for qualifications says two phases of the Peter Jenkins Greenway were already built. It describes the new TAP-funded project as the piece that connects them, and it places the work within the city's Bicycle and Greenway Plan.
A May 2024 scope of work from Kimley-Horn lays out the route as roughly 0.85 miles:
The same scope lists items the design team expected to study. These include a possible pedestrian bridge over an unnamed tributary of Grassy Branch, possible boardwalk sections, a traffic-engineered crossing at Duplex Road, bike facilities on Hurt Road and Prescott Way, and ADA upgrades to existing sidewalks, curb ramps, signs, and striping. Those were assumptions at the start of design. Final plans could look different.
The grant timeline was explained publicly when the city first weighed the application. At a joint meeting of the Board of Mayor and Aldermen and the Planning Commission, Economic Development Director Kayce Williams presented the connector. She said it would join two separate sections of the walkway, give students a better walking route to Allendale from both north and south, and open pedestrian access to the new multi-use trail on Duplex Road. The Daily Herald quoted her on where the project ranked:
"This connector happens to be numbers two and three on that priority list, and so that's a good thing. We're following our plan that we put in place."
The same article put the estimated cost at about $1.25 million. The grant would cover roughly 80% of construction costs. Design and right-of-way, estimated at $650,000, would fall to the city, bringing its total share to about $900,000. Planning Commission Vice-Chair James Golias described the schedule: three years to get a project ready for construction after accepting the money, then two more years to build it, or "almost five-and-a-half years" from application to completion.
Those 2021 figures were early estimates. The real point of that meeting is the sequence. Federal money pays for building the trail, but the environmental review, design, and land acquisition have to be finished first, in order, with TDOT reviewing each stage.
Spring Hill has a second project on the same track, the Harvey Park Greenway. Here are the two side by side, based on the city's FY 2025–26 capital projects report and the Parks and Recreation staff report dated September 14, 2026.
| Peter Jenkins Greenway Connector | Harvey Park Greenway | |
|---|---|---|
| Length | About 0.85 miles | About 1.3 miles |
| Design consultant | Kimley-Horn | Verdantas |
| Original forecast | Almost five and a half years from application to completion, as described in 2021 | Construction in fall 2023, finished by spring 2025 |
| Environmental review | NEPA approval received | NEPA approval received |
| Design | Notice to proceed issued July 13, 2026 | About 80% complete |
| Latest report | Waiting on TDOT feedback on preliminary design | TDOT reviewing the Transportation Management Plan with right-of-way plans; city hoped for final right-of-way plans in October |
| Before construction | Right-of-way acquisition | Right-of-way acquisition, then bidding |
The bottom row is the same for both projects. Each must buy the land or easements it needs before anything can be built.
The Peter Jenkins connector also faced a deadline. The June 8, 2026 staff report said TDOT had confirmed on May 6 that it received updated environmental forms. One response still needed revision, and the city was "monitoring it closely" because its contract required a design notice to proceed by September 30. The notice went out on July 13, with more than two months to spare. By September, the consultant had sent the city's finance department an updated budget broken out by phase, and staff were still waiting to hear back from TDOT on the preliminary design.
The Harvey Park Greenway is older and further along, and it is the closer of the two to the right-of-way stage.
In October 2020, The Daily Herald described the proposed route. It would start at Harvey Park on Miles Johnson Parkway, follow McCutcheon Creek past the Autumn Ridge tree line, run behind Lowe's and parallel to Main Street, pass behind Walmart and Publix, and end at Wilkes Lane. That year, Williamson Source reported a TAP award of $1,195,998 for the work along the creek, covering signage, landscaping, crosswalks, median islands, pedestrian bridges, and ADA compliance. The Daily Herald reported a separate $598,808 in federal funds for engineering and right-of-way.
A March 16, 2026 staff memo explains how the money is split. Surface Transportation Block Grant funds pay for the NEPA design phase and right-of-way. TAP funds pay for construction and construction inspection. Both require an 80% federal and 20% local share. The memo also says the grant contract expired on December 31, 2025, and that the city had to ask TDOT for an amendment to extend the schedule and stay eligible for the federal money.
The June staff report describes the back-and-forth that followed. Once the NEPA reevaluation was approved, the consultant asked TDOT "repeatedly for over a month" what came next. On April 28, TDOT replied that it needed the extension letter and an updated schedule. The board approved the amendment on May 18 and sent it to TDOT. The capital report adds that a separate application for construction grant funds will be submitted. Neither city report gives a revised construction date for either greenway.
The paths already on the ground came mostly from road projects and neighborhood efforts. TDOT's Duplex Road project improved a 3.2-mile stretch from Main Street to just west of the I-65 overpass and added sidewalks and a multi-use path, according to the engineering firm Gresham Smith. When the Daily Herald reported on the widening in 2021, it had just been finished after 14 years of planning, land acquisition, and construction, at a cost of about $12 million. Inside Wyngate Estates, the Peter Jenkins Walking Trail runs through about 17 acres of community open space in a 555-home subdivision off Duplex Road.
New development adds more. In both the June and September 2026 staff reports, Parks and Recreation Director Kayce Williams said she continues to work with the planning department and applicants so that greenways, bike lanes, and multi-use trails are built by development as the Bicycle and Greenway Plan lays out. Short pieces arrive when a subdivision is built. The longer links that cross Duplex Road or run behind the Main Street shopping centers wait on TDOT reviews, and both still have right-of-way to acquire after those reviews.
If you live near Baker Springs, Benevento, Wyngate, or the McCutcheon Creek corridor and want to know how a planned greenway link could affect your street or your plans for your home, I'm happy to talk it through. Gabrielle Grooters follows these city projects closely, and you can schedule a free consultation anytime.