Two-story brick home with white window trim, a deep green front lawn, a concrete approach, and a mature maple in soft afternoon light.

The I-65 Widening Spring Hill Just Got Is a 2030 Fix on a 2028 Clock

October 15, 2026

On September 30, 2026, the Greater Nashville Regional Council's Transportation Policy Board adopted a resolution adding TDOT's I-65 widening, from near Saturn Parkway to near the I-840 interchange, to the region's Transportation Improvement Program. The total is $150 million, all of it state money. It covers the stretch most Spring Hill commuters drive every weekday on the way toward Franklin and Nashville.

TDOT describes the project in plain terms. It is a short-term improvement, designed to cut delays the department projects for 2030, and a much larger corridor study that is already underway will treat it as a future baseline condition. The money is committed, and the long-term plan for this stretch of I-65 is still being written.

What $150 Million Covers Between Saturn Parkway and I-840

The TDOT project page lists four pieces of work:

  • Added through lanes. At least one more lane in each direction, from north of the Saturn Parkway interchange to the I-840/I-65 interchange.
  • Auxiliary lanes. Extra lanes between June Lake Boulevard and I-840.
  • A new Thompson's Station Road overpass. The existing overpass will be replaced to make room for the wider interstate and for a possible future widening of Thompson's Station Road East.
  • New I-65 bridges over US-431. The interstate bridges over Lewisburg Pike will be rebuilt so US-431 can be widened later if needed.

The auxiliary lanes begin at the city's newest exit. The June Lake Boulevard interchange at Buckner Road opened to drivers on May 31, 2024, as NewsChannel 5 reported at the time. Spring Hill and TDOT split the cost. NewsChannel 5 put it at roughly $55 million, and the city later gave a final total of $56.8 million, helped by a $25 million federal BUILD grant. BELL Construction was the design-builder. Its contract covered design, right-of-way, permits, utilities and construction.

That interchange added an exit between Saturn Parkway and I-840. The auxiliary lanes in the new plan are the stretch of interstate built around the traffic entering and exiting there.

The bridge replacements are designed with a later decision in mind. The new Thompson's Station Road overpass and the new Lewisburg Pike bridges are sized for local roads that might be widened someday. TDOT's page calls those widenings "potential," and neither one is part of this project.

Why TDOT Calls It Short-Term

The project traces back to December 2025. That month TDOT finished an Operational Improvement Study for this section of I-65, looking for short-term improvements to reduce the delays it projects for 2030. The department's page states that this area has "an immediate need for short-term improvements," and says the project is meant to reduce delays between the Saturn Parkway and I-840 interchanges.

The 2030 date matters for planning. Construction is scheduled to begin in 2028, which leaves a short window before the delay forecasts that justified the project come due. TDOT has not published a summary of the December 2025 study, its delay figures, or its full list of recommended measures. The project page describes the purpose without the underlying numbers.

The page also says the widening "will not preclude future corridor improvements" that come out of the larger I-65 study. In planning terms, the added lanes become the baseline that every later option for this stretch gets measured against.

The Calendar Between Now and Construction

TDOT is delivering the job through its Alternative Delivery program, which lets one design-builder handle both design and construction. That is the same model used for the Buckner interchange. The project is currently in procurement. TDOT's forecast milestones are below, and the department notes that all of these dates may change:

  1. Q3 2026: Request for Qualifications. This quarter ends in September, so it is already behind us as of mid-October 2026.
  2. Fall 2026: Design evaluations begin.
  3. Q2 2027: Request for Proposals.
  4. Q3 2027: Design-builder awarded.
  5. 2028: Construction begins.

The funding follows the same schedule. Of the $150 million, $10 million is assigned to preliminary engineering and design in fiscal year 2026, and $140 million to construction in fiscal year 2028. Before the amendment, the project was listed in the regional program as "new" with no money attached.

Spring Hill Mayor Matt Fitterer sits on the board that voted. Main Street Maury quoted him on the result:

"[We] allocated $150,000,000 to adding lanes to I-65 between Saturn Parkway and I-840. The project is now fully funded through construction."

"Fully funded through construction" means the money for every phase is now committed. No published date yet says when the new lanes will open to traffic.

The Larger I-65 Study Running Alongside It

A second and much larger plan is moving on its own schedule. TDOT's I-65 Corridor Planning and Environmental Linkages study, known as the PEL study, covers I-65 from Thompson Lane in Davidson County to Bear Creek Pike in Maury County. That takes in Davidson, Williamson and Maury counties. TDOT plans to carry the study's recommendations into the federal environmental review process.

The first round of public meetings took place in August 2026, on August 13, 17 and 18, in Spring Hill, Nashville and Franklin. Comments were accepted through September 8. The study's exhibits point to problems along the whole corridor, including acceleration and deceleration lanes, interchange spacing and vertical clearances. The public materials do not say which of those apply to the Spring Hill and Thompson's Station stretch.

Here is how the two plans compare, based on TDOT's published materials:

Saturn Pkwy to I-840 widening I-65 Corridor PEL study
Limits North of SR-396 to the I-840 interchange Thompson Lane in Davidson County to Bear Creek Pike in Maury County
Purpose Short-term relief for delays projected for 2030 Corridor-wide needs and alternatives
Status In procurement, fully funded First public meeting round complete
Next milestone Design-builder award, Q3 2027 Second meeting round and report, tentatively Q1 2027
Shovels Construction scheduled for 2028 No construction phase defined yet

The next round of PEL meetings, tentatively planned for the first quarter of 2027, will come before the design-builder for the widening is chosen. Spring Hill residents will have a chance to comment on the long-term corridor while the short-term project is still in procurement.

What Neighboring Officials Raised at the August Meetings

The bridge replacements tie this project to the local roads that cross I-65. The Williamson Herald's report on the August PEL meetings covered those connections. Thompson's Station Mayor Brian Stover told the paper that his town, which sits between Spring Hill and Franklin, should be represented in the process. He asked for coordination and said Highway 431 deserves attention alongside I-65. In the same report, Franklin Mayor Ken Moore asked for a close look at every interchange and at transit alternatives. TDOT's Erin Zeigler described the June Lake project as adding a lane in each direction plus an auxiliary lane.

Highway 431 is Lewisburg Pike, the road under the interstate bridges this project replaces. TDOT is rebuilding those bridges so US-431 could be widened later, and the new Thompson's Station Road overpass is designed the same way. Whether either local road is actually widened will be decided separately. The I-65 project is building the space for it now.

For Spring Hill commuters, the dates to watch are the design-builder award in Q3 2027, the second PEL meeting round tentatively planned for Q1 2027, and the 2028 construction start. TDOT's project contact for the widening is Jonathan Vogel, the Region 3 Alternative Delivery Project Manager, who is listed on the project page.

Your daily drive on I-65 is part of what living in Spring Hill costs you, and these projects will shape it for years. If you'd like to talk through how the Saturn Parkway-to-I-840 schedule fits your own plans, Gabrielle Grooters is happy to set up a free consultation and go over what the timeline means for your corner of town.

Partner With Me

I blend proven market strategies with a passion for interior design to showcase your home at its best and help you move with confidence. Every detail matters—and I'm here to ensure your journey is smooth, supported, and beautifully executed.